Sunday, July 4, 2010
Wednesday, June 23, 2010
Overdue Update
Saturday, June 5, 2010
First floor framing done...
Monday, May 24, 2010
Progress
Saturday, May 22, 2010
Subfloor
Tuesday, May 11, 2010
Unfortunately I am now back at work, but the work has continued... Dan, Joe and Dani having been graciously putting in lots of overtime at the house!


Dan and Joe dug the trench to run electricity down from the road last night...

First load of lumber has arrived!

Foundation waterproofing is on and the footing drain is in. You can see the risers showing where we will stub in the drains for the gutters eventually...

Walkout end with some back fill now in to start leveling it up...

Dani and Joe spent Saturday laying the radiant PEX tubing that will run throughout the basement floor...


With a few delays due to pump clogging we got the walls poured just in time before a big rain...


Dan and Joe dug the trench to run electricity down from the road last night...

First load of lumber has arrived!

Foundation waterproofing is on and the footing drain is in. You can see the risers showing where we will stub in the drains for the gutters eventually...

Walkout end with some back fill now in to start leveling it up...

Dani and Joe spent Saturday laying the radiant PEX tubing that will run throughout the basement floor...


With a few delays due to pump clogging we got the walls poured just in time before a big rain...
Sunday, May 2, 2010
Walls are ready...
We ended up with a foot of snow on Wednesday and then 85 degrees on Sunday. Luckily the snow didn't stick around too long, but it was enough to push us back a few days. Walls are ready for concrete and we will be using a boom pump tomorrow to fill them up.
The ICF's went together pretty smoothly, once we got a few rows set a level they flew up, took us a little longer to fit the walk out door and windows in, but it all worked out well.
Also managed to get the footing drain in today, now we will be ready to back fill when our concrete is all set up.
Labels:
concrete,
foundation,
hinesburg,
ICF,
vermont farmhouse